‘Rayalaseema Rising’.. Rs 1 Lakh Crore Promises, But Questions Over Shifting of Key Projects

‘Rayalaseema Rising’.. Rs 1 Lakh Crore Promises, But Questions Over Shifting of Key Projects

The Andhra Pradesh government has announced plans to undertake a series of development projects under the ambitious ‘Rayalaseema Rising’ initiative, with an estimated outlay of around Rs 1 lakh crore. The programme is being projected as a major push to transform Rayalaseema into a hub for horticulture and other development activities.

However, concerns are being raised over the ground-level status of several projects considered crucial to the region. Critics allege that important irrigation projects, educational and medical institutions, banking facilities and industrial centres are either being delayed or shifted to other parts of the state.

Rayalaseema Lift Irrigation Project Faces Uncertainty

The reported slowdown in the Rayalaseema Lift Irrigation Project (RLIP) has become a major concern among farmers and regional leaders. It has been claimed that nearly 80 per cent of the project works had been completed during the previous government’s tenure, but the remaining works have now come to a standstill.

The issue has assumed significance as irrigation remains one of the biggest requirements of the drought-prone Rayalaseema region. Farmers are also questioning why water is not reaching the KC Canal ayacut despite adequate water levels being maintained at the Srisailam reservoir.

Projects and Institutions Being Shifted

Several decisions concerning educational, medical, banking and industrial institutions have also triggered criticism.

The National Institute of Electronics and Information Technology (NIELIT), which was sanctioned for Tirupati, has reportedly been shifted to Amaravati. Similarly, the proposed AIIMS for Anantapur was shifted to Mangalagiri.

The government’s handling of the 50 MBBS seats sanctioned for Pulivendula Medical College has also become a subject of discussion in the region, with questions being raised over the status of the allocation.

AP Grameena Bank Headquarters Shift

Another contentious issue is the decision to shift the headquarters of Andhra Pradesh Grameena Bank from Kadapa to Amaravati.

Critics argue that Kadapa has historically served as an important banking and administrative centre for the region and question the rationale behind moving the headquarters away from Rayalaseema.

MSME Technology Centre Shifted From Kopparthi

The proposed MSME Technology Centre at the Kopparthi Mega Industrial Hub has also reportedly been shifted to Amaravati.

Kopparthi was being developed as a major industrial destination in the region, and the proposed technology centre was expected to support micro, small and medium enterprises. Its relocation has therefore raised concerns over the development of the industrial ecosystem in Rayalaseema.

Pulivendula Mega Water Grid Raises Questions

The Pulivendula Mega Water Grid Project is another project being cited by regional leaders.

While it has been claimed that nearly 80 per cent of the works had already been completed, officials have indicated that the remaining works could take another two-and-a-half years to complete.

This has led to questions over the pace of execution of projects that are directly connected to drinking water and the basic needs of people in the region.

Bullet Train and Hyperloop Proposals vs Immediate Needs

The government’s promotion of ‘Rayalaseema Rising’ through large-scale events has also attracted criticism over its focus and priorities.

Proposals involving futuristic transport concepts such as bullet trains and hyperloop systems have been highlighted as part of the broader vision for Rayalaseema. At the same time, critics point to delays or reported relocations involving irrigation, education, healthcare, industries and employment-related projects.

They question whether the region’s immediate needs should receive greater attention before focusing on long-term and futuristic infrastructure proposals.

Water, Agriculture, Education and Jobs at the Centre of Debate

Rayalaseema is a drought-prone region where water security remains closely linked to agriculture and livelihoods. Critics argue that development in such a region cannot be measured only through large announcements, investment summits or high-profile events.

According to them, sustainable development should also focus on irrigation, drinking water, agriculture, education, healthcare, industrialisation and employment opportunities.

Rayalaseema Rising: Promise and Ground Reality

The debate surrounding ‘Rayalaseema Rising’ is therefore increasingly centred on the gap between the government’s stated vision and the status of projects on the ground.

While the government is projecting a large-scale development roadmap involving an estimated Rs 1 lakh crore, critics are questioning delays in key projects and the reported relocation of institutions and facilities from Rayalaseema.

The central issue now is whether the ambitious objectives announced under Rayalaseema Rising will translate into tangible improvements in irrigation, agriculture, education, healthcare, industries and employment opportunities for the people of the region.

Join WhatsApp

Join Now

Leave a Comment